Observe procedure for REPAIR STAGE 3.
Read contents of BODY, GENERAL.
Following new body parts are required:
Removing the engine support side frame connection: Open welded connections in areas (1).
Open welded connections in areas (1).
Remove engine support/side frame (2).
Open welded connections in areas (1).
Remove reinforcement (2).
New part preparation
Open welded connections in areas (1).
Remove engine support (2).
Installing the engine support side frame connection
Install and weld new parts.
NOTE: First, the reinforcement of the engine support side frame connection must be installed and welded for reasons of accessibility as a separate component.
NOTE: The bulkhead cross member (1) is filled with low-flammable cavity foam.
In case of smoke formation, stop the welding procedure and cool the welded area with compressed air if applicable.
REPLACING ENGINE SUPPORT/FRONT RIGHT SIDE FRAME CONNECTION (FRONT RIGHT WHEEL ARCH REMOVED)
The work is identical to replacing the "ENGINE SUPPORT FRONT LEFT SIDE FRAME CONNECTION".
BMW X3 Service & Repair Manual > Front axle: Tool set
Tool set Mechanical tool
NOTE:
Retrofit - for authorised BMW dealers who have already received the special
tool 31 0 000 from SPX
SI number
01 19 10 (674)
Tool set AM
NOTE:
Threaded spindle set for removing and installing the rubber mount on the rear
axle support.
SI nu ...